A nuclear renaissance fuels research potential and growth at McMaster University

This article was written by Joe Friesen and was published in the Globe & Mail on January 12, 2026.

A blue glow emanates from the core of the McMaster Nuclear Reactor, which provides neutrons for research and medical isotope production at McMaster University’s campus in Hamilton.

Funding and new minor studies program attract students keen to work in industry

A mesmerizing deep blue glow emanates from the nuclear reactor nestled in the heart of the campus at McMaster University in Hamilton.

Sunk 10 metres beneath the surface of a pool of water, encased in an air-locked, 15-sided, concrete building, the uranium fuel generates enough power to heat hundreds of homes.

But its significance to the university is far more about its research potential than its three megawatts of power.

At a time when nuclear power is in the midst of a renaissance, McMaster is wrapping itself in the label of Canada’s nuclear university.

The school launched a minor in nuclear studies in the fall and plans for a bachelor’s degree in nuclear engineering are in the works. Last term, 148 students signed up for a new interdisciplinary course on nuclear technology applications. Meanwhile, the university’s reactor produces about 60 per cent of the world’s supply of iodine-125, a medical isotope used for cancer treatment. And its new president, Susan Tighe, is bullish about nuclear’s role in driving the university’s ambitions.

“I think nuclear has great potential from a research perspective, as well as commercialization,” Dr. Tighe said. “And it’s great training for our students.”

Dr. Tighe, who became president of McMaster in July, is the first engineer to hold the top job at the university.

Having previously been provost at McMaster for five years she’s conscious of the financial clouds hanging over the university sector and says she’s determined to keep McMaster operating within its means. She’s proud to note that the school ran a surplus in 2025 and is among the handful of Ontario universities operating in the black.

“What I like to say is we’re a public sector organization that operates with private-sector principles,” she said. “We’re trying to be responsible with what we get.”

In September, the Ontario government announced $18-million in funding to allow McMaster to operate the nuclear reactor around the clock, seven days a week, up from five days. The extended hours will also allow it to boost production of medical isotopes that are crucial to cancer care and to expand research and training opportunities for students.

“We do have this unique research facility, and given that we’ve had support from the provincial government to operate 24 hours a day, it’s enabling more access to the reactor,” Dr. Tighe said.

The McMaster nuclear reactor was built in 1959, when the university had begun to grow beyond its Baptist roots. The project was spearheaded by Harry Thode, a Canadian nuclear pioneer who worked on the Canadian branch of the Manhattan project in the Second World War. He later served as president of the university from 1961 to 1972.

“For Canada to put a research reactor on a campus at that time was really visionary,” said David Novog, a physics professor, who has been leading tours of the reactor since the 1990s.

Prof. Novog said he first came to McMaster as a grad student because he was drawn by the chance to work on the most powerful research reactor on a Canadian campus. He explains that the blue light that surrounds the low-enriched uranium fuel cells in the water of the reactor pool is actually Cherenkov radiation, named for a Nobel-winning Soviet scientist.

Today Prof. Novog supervises grad students such as Jessica Lo, who is looking into neutron imaging of fuel bundles.

She decided to go into the nuclear field after finishing an undergraduate degree in physics. “There’s no other school that compares to McMaster. You have a reactor right on campus,” Ms. Lo said.

The reactor has a few dozen students working at various times in the week, often using its rays for imaging, particularly for close examination of turbine blades.

They also study health physics, looking at the impact of radiation on humans. And there are research applications for mining, too.

For Arianna Santos, a fourthyear engineering student, the chance to attend a university with a nuclear reactor was also too good to pass up.

Ever since watching science shows on television when she was young she has been captivated by nuclear’s potential to serve the world’s energy needs with a minimum of greenhouse gas emissions.

“I’ve been told that all the energy a person needs for their life on Earth could be contained in a single soda can of uranium,” she said.

Many of today’s students would be too young to remember some of the disasters that have led to public skepticism about nuclear technology: notably, the reactor meltdown in Fukushima, Japan, following a 2011 earthquake and the explosion in Chernobyl, Ukraine of the Soviet-built reactor in 1986.

Ms. Santos recognizes there’s public anxiety about the technology. But she feels reassured by the extensive safety protocols in nuclear facilities.

“These buildings are really, really safe,” she said.

Ms. Santos is one of about 150 students who’ve signed up for McMaster’s new minor in nuclear studies. She’s also a member of McMaster’s nuclear club, where students network and explore job opportunities.

Last summer she conducted research in nuclear science, working with a hot cell where she used mechanical arms to manipulate radioactive material. Her dream after graduation is to pursue a career in the nuclear field.

“This small atom, you just split it and it releases so much energy and heat that we barely have to use any uranium. It’s amazing, it’s crazy, it’s fascinating.”

Spend­ing big on nuc­lear

Ontario is invest­ing bil­lions into react­ors — even as the rest of the world turns to solar and wind. Is this the wrong bet?

The Darlington Nuclear Station is the site of four planned new small nuclear reactors — one facet in Ontario's massive nuclear buildout.

This article was written by Marco Chown Oved and was published in the Toronto Star on January 11, 2026.

In the race to pre­pare for an elec­tri­fied future of AI, data centres, EVs and heat pumps, Ontario has placed a big bet on nuc­lear.

With more than $73 bil­lion com­mit­ted to build­ing new and refur­bish­ing old react­ors — and two more plants in the pipeline that could add tens of bil­lions more — Ontario tax­pay­ers are count­ing on nuc­lear energy to pay off for dec­ades to come.

Widely hailed for its abil­ity to provide massive amounts of stable, emis­sions ­free power that the province will need to elec­trify the eco­nomy, nuc­lear has emerged as a solu­tion advoc­ates say is cru­cial to avoid the worst effects of cli­mate change — all while sup­port­ing a well­ estab­lished local industry. A single nuc­lear plant can provide the same amount of power as tens of thou­sands of solar pan­els and wind tur­bines — even when the wind isn’t blow­ing, and the sun isn’t shin­ing.

Prime Min­is­ter Mark Car­ney and Premier Doug Ford announce expan­sion plans at the Dar­ling­ton energy plant last fall.

“Nuc­lear brings a set of attrib­utes and char­ac­ter­ist­ics that you really can’t find with any other gen­er­at­ing source,” said Brendan Frank, Dir­ector of Policy and Strategy at Clean Prosper­ity, a cli­mate policy think tank. It’s large scale, clean and reli­able with a small land foot­print, he says. “There’s a lot to like about nuc­lear.”

But the prom­ise of nuc­lear power is tempered by the poten­tial for peril.

Crit­ics say nuc­lear pro­ponents have never been able to address exist­ing react­ors’ sig­ni­fic­ant short­com­ings, includ­ing dec­ade ­long con­struc­tion timelines, con­sist­ently large cost over­runs, and the tiny but nonzero risk of cata­strophic acci­dents. The cost con­sid­er­a­tions alone risk under­min­ing the fight against cli­mate change by mak­ing clean power more expens­ive than burn­ing fossil fuels.

“Baked right into the nuc­lear option is cent­ral­iz­a­tion, a reli­ance on tech­nical elites, the need for long ­term stew­ard­ship and para­mil­it­ary secur­ity, a low tol­er­ance for fail­ure, and the accept­ance of unin­sur­able risks,” said Ralph Tor­rie, the head of research with Cor­por­ate Knights and a vet­eran energy ana­lyst.

And unlike nuc­lear oppon­ents of the 1980s, today’s crit­ics have a ready altern­at­ive in renew­able energy, which is being built at an unpre­ced­en­ted speed and scale all over the world. Last year, more than 90 per cent of new power brought online glob­ally has been wind and solar. Mean­while, the nuc­lear industry has been mired in a 25 ­year decline with more react­ors decom­mis­sioned than built, accord­ing to the Inter­na­tional Atomic Energy Agency.

Nuc­lear power is yes­ter­day’s tech­no­logy, the crit­ics say.

“Every dol­lar we spend on new nuc­lear plants or recon­di­tion­ing 20th­cen­tury nuc­lear steam gen­er­at­ors drives up the cost of build­ing a sus­tain­able energy sys­tem in Ontario and puts us fur­ther behind in the energy trans­ition that is a defin­ing fea­ture of suc­cess­ful 21st­ cen­tury eco­nom­ies,” Tor­rie said.

In the search for cli­mate solu­tions, the debate over nuc­lear power is par­tic­u­larly acute. For pro­ponents, global warm­ing can­not be addressed without a nuc­lear renais­sance. For oppon­ents, nuc­lear is a trap that diverts resources from bet­ter solu­tions while com­mit­ting us for dec­ades to a tech­no­logy that has never lived up to its prom­ises.

And Ontario has already picked its side.

“We’re doub­ling down on nuc­lear,” Energy Min­is­ter Stephen Lecce told the Star in an inter­view.

“If you care about jobs for Cana­dians, if you care about an eth­ical sup­ply chain using a clean grid, not a coal­fired grid, if you care about human rights, the rule of law, fun­da­mental Cana­dian val­ues, and the eco­nomic advant­ages for the work­ers, for the women and men who work in this province, then you will unapo­lo­get­ic­ally defend and pro­mote Ontario’s nuc­lear advant­age, which is now an envy of the world.”

Why nuc­lear is con­sidered a `very expens­ive’ option

This June, the province laid out a 25­ year road map for the elec­tri­city sys­tem that relies over­whelm­ingly on nuc­lear. It projects a massive 75 per cent increase in demand for power, the equi­val­ent of adding four­ and ­a ­half Toron­to’s to the grid. While there have been some invest­ments in bat­tery stor­age and hydro, most of this energy will come from refur­bish­ing the exist­ing fleet of react­ors and build­ing new ones, includ­ing one in Wes­leyville — on the shore of Lake Ontario to the east of the exist­ing Pick­er­ing and Dar­ling­ton plants — that would be the world’s biggest nuc­lear plant. In doing so, the province would triple its nuc­lear gen­er­a­tion, exceed­ing the entire elec­tri­city sys­tem’s out­put today.

“Ontario is put­ting a lot of eggs in a very expens­ive bas­ket,” said David Pickup, an energy ana­lyst at the Pem­bina Insti­tute and the author of a report high­light­ing the risks of the province’s nuc­lear build out.

“The gov­ern­ment recog­nizes that hav­ing low rates is really crit­ical,” he said. “So it is kind of baff­ling to us that there’s such a strong focus on new nuc­lear projects.”

The price tag for this nuc­lear pivot hasn’t been fully cal­cu­lated. The four new Small Nuc­lear React­ors (SMRs) at Dar­ling­ton have a budget of $21 bil­lion. The Pick­er­ing refur­bish­ment is expec­ted to cost $26.8 bil­lion. The refur­bish­ment of Bruce Power’s nuc­lear plant has a $13­ bil­lion budget. Dar­ling­ton’s refur­bish­ment is cur­rently pro­jec­ted to be com­pleted on budget at $12.8 bil­lion. No price tag has been announced for new nuc­lear plants at Wes­leyville and Bruce, which could add tens of bil­lions more to the total.

That could bring the nuc­lear con­struc­tion budgets north of $100 bil­lion, a sim­ilar scale of invest­ment as the $116 bil­lion announced for all 11 nation­build­ing projects announced by Prime Min­is­ter Mark Car­ney’s Major Projects Office this fall (which included sup­port for Ontario’s SMRs). Even that colossal amount of money could prove to be a best­case scen­ario, because nuc­lear projects world­wide have often suffered from severe cost over­runs that, on aver­age, lead to a doub­ling of their ori­ginal budgets.

The only new nuc­lear react­ors built in the E.U. or North Amer­ica this cen­tury char­ac­ter­ize this trend. The Vogtle plant in Geor­gia cost more than twice as much as budgeted; in Fin­land, the Olkiluoto plant came in at four times the ori­ginal budget; and in France, the Flaman­ville reactor’s final cost was seven times greater than expec­ted.

Using real­world costs of recently com­pleted nuc­lear projects, York Uni­versity Pro­fessor Mark Win­field cal­cu­lated that Ontario’s full nuc­lear build out could cost as much as $400 bil­lion, all of which would have to be paid for through increases to hydro rates — something that’s been polit­ic­ally toxic in Ontario.

For his part, Lecce says Ontario can and will do bet­ter — and has proven it dur­ing the last dec­ade of refur­bish­ments.

“I’m aware of the global real­ity. But here at home, we’re doing something right,” he said. “We’ve been doing large­ scale refur­bish­ments of some of the largest nuc­lear react­ors on the con­tin­ent ahead of sched­ule and on budget, unit by unit. From Bruce Power to Dar­ling­ton, we have demon­strated project dis­cip­line.”

Ontario Power Gen­er­a­tion (OPG), which owns and oper­ates all the province’s nuc­lear react­ors except for those at Bruce, declined to com­ment for this story.

Lecce says that the risk is worth it, not only to provide the power needed to expand Ontario’s min­ing, refin­ing and man­u­fac­tur­ing sec­tors, but also to sus­tain a nuc­lear industry whose expert­ise can be expor­ted.

The nuc­lear industry cur­rently con­trib­utes $22 bil­lion annu­ally to Canada’s GDP and employs more than 89,000 people, the major­ity in Ontario, accord­ing to the Cana­dian Nuc­lear Asso­ci­ation. The Ontario build out prom­ises to add tens of thou­sands of tem­por­ary con­struc­tion and per­man­ent oper­a­tion jobs and bil­lions in eco­nomic bene­fits to that total.

“Ninety per cent of the spend is stay­ing in the province,” said Lecce. “This is the obvi­ous path for­ward.”

Why the nuc­lear option has com­pet­i­tion in wind and solar

While Ontario has for dec­ades been Canada’s leader in nuc­lear, the province was also, briefly, the nation’s leader in the con­struc­tion of wind and solar.

But when Doug Ford was elec­ted premier, he can­celled every renew­able project in the pipeline — some of which were par­tially built — at a cost of $231 mil­lion. In the sev­en ­and ­a­ half years since, as renew­ables have come to dom­in­ate new global power projects, not a single new renew­able energy project has been com­mis­sioned in Ontario.

Mean­while, thanks to aggress­ive Chinese indus­trial policy, the cost of build­ing new renew­able power has dropped by 70-­90 per cent over the last dec­ade, to the point that wind and solar are now the cheapest ways to gen­er­ate elec­tri­city in most coun­tries in the world, accord­ing to the Inter­na­tional Energy Agency.

Not only that, but renew­ables are far faster to build than nuc­lear plants and can be deployed quickly as demand grows, instead of wait­ing for lengthy nuc­lear builds — and burn­ing more nat­ural gas in the mean­time.

This is why renew­ables are win­ning out world­wide, said phys­i­cist and energy ana­lyst Amory Lov­ins in a recent art­icle.

“Each year, nuc­lear adds as much net global capa­city as renew­ables add every two days,” wrote Lov­ins, who co­foun­ded the Rocky Moun­tain Insti­tute.

Only five years into a global renew­able build­ing spree, wind and solar have already far sur­passed total nuc­lear gen­er­a­tion, which took 65 years to build. “Soar­ing renew­ables gen­er­ate three times more global elec­tri­city than stag­nant nuc­lear power,” Lov­ins wrote. “In 2023-­24, China added 197 times more solar and wind than nuc­lear capa­city, at half the cost.”

Des­pite being elec­ted on a plat­form hos­tile to renew­ables, even Ford has come around, issu­ing a round of pro­cure­ment that could end up includ­ing wind and solar.

But the idea that the debate is settled and that renew­ables are cheaper and bet­ter is something the nuc­lear industry in gen­eral, and the pro­vin­cial gov­ern­ment in par­tic­u­lar, pushes back on.

Renew­ables are “con­trolled by the Chinese, man­u­fac­tured there, by an uneth­ical regime using coal fired power to drive their pro­duc­tion. In what world is that product from that nation with that human rights record adding any value to Canada?” Lecce said, adding: “This nar­rat­ive that the altern­at­ive of wind and solar is cheaper is demon­strably false.”

The import­ant ways nuc­lear is dif­fer­ent than wind and solar

Cost com­par­is­ons between nuc­lear and renew­ables get muddy because they’re not apples to­ apples.

Nuc­lear provides inex­pens­ive and stable base­load power, but is dif­fi­cult to ramp up and down to meet demand.

Renew­ables can provide cheaper power, but only inter­mit­tently — when the wind blows, and the sun shines. They become “dis­patch­able” when they’re paired with bat­ter­ies that are charged when the power isn’t needed and dis­charged back into the grid when it is.

A study pre­pared by the IESO last sum­mer found that renew­ables paired with bat­ter­ies can provide dis­patch­able power for less than half the cost of nuc­lear. This scen­ario becomes even more bene­fi­cial if nat­ural gas is kept as a backup and excess gen­er­a­tion is expor­ted for profit.

The same study found, however, that nuc­lear SMRs will pro­duce base­load power for about two thirds the cost of renew­ables and bat­ter­ies.

But price isn’t the only con­sid­er­a­tion that Lecce says favours nuc­lear.

Unlike wind tur­bines and solar pan­els, which typ­ic­ally have a com­mer­cial lifespan of 20­-25 years, nuc­lear react­ors can last “80 to 90 years,” Lecce said.

And if Ontario were to build renew­ables instead of new nuc­lear plants, it would require sig­ni­fic­ant “over­build” to make up for the inter­mit­tency of wind and solar — five to seven times more gen­er­a­tion, accord­ing to the IESO.

To accom­mod­ate that over­build, the energy min­istry estim­ates it would need to set aside approx­im­ately 100 times more land for solar and 500 times more land for wind to gen­er­ate the same amount of power as a poten­tial 10,000 MW nuc­lear sta­tion at Wes­leyville.

Cor­por­ate Knights’ Tor­rie said these argu­ments rely on fanci­ful assump­tions that “tilt the scales” in favour of nuc­lear.

A 90 ­year lifespan is unreal­istic, he said, con­sid­er­ing no nuc­lear plant in the world has ever oper­ated for even 60 years. None of Ontario’s fleet of Candu react­ors has reached 45 years of oper­a­tion, he said.

“Can­dus typ­ic­ally have to be rebuilt when they are 20-­25 years old, and so far the longest any Candu has oper­ated after being rebuilt is 23 years. We are not even close to being able to say with con­fid­ence a Candu will last for 60 years, even with a com­plete rebuild along the way,” he said.

Solar pan­els, by con­trast, may be guar­an­teed by the man­u­fac­turer to last 25 years, but have a track record of func­tion­ing far longer than that.

“Solar pan­els slowly lose effi­ciency over time,” said Tor­rie.

“But they can be oper­ated for dec­ades after they have paid for them­selves.”

A recent study found a 30­ year old solar install­a­tion in Switzer­land was still pro­du­cing at 80 per cent of its ori­ginal out­put. In New Hamp­shire, a single rooftop panel was still pro­du­cing power after more than 40 years. The first mod­ern solar cell, pro­duced by Bell Labs in 1954, still gen­er­ates elec­tri­city, more than 70 years after it was man­u­fac­tured.

Unlike nuc­lear plants, solar pan­els don’t require any fuel, so even with a lower out­put, the elec­tri­city they pro­duce is close to free.

As for the issue of land use, Tor­rie invites any­one to visit a wind farm and look at how much space is between the tur­bines — space that’s used to graze live­stock or grow food.

“For solar, the pan­els are often installed on rooftops, where they have zero land impacts. Solar farms are now being built on agri­cul­tural land without tak­ing it out of pro­duc­tion, and these `agro­solar’ projects are gen­er­at­ing new income streams for farm­ers.”

By con­trast, while the foot­print of a nuc­lear facil­ity may be small, it’s off lim­its to any other use and the long­term stor­age of highly radio­act­ive spent nuc­lear fuel requires set­ting aside land for tens of thou­sands of years.

`Energy secur­ity is national secur­ity’

Even among nuc­lear pro­ponents, Ontario’s choice of an Amer­ican reactor design for the SMRs has raised eco­nomic and secur­ity con­cerns. Unlike the exist­ing fleet of Cana­dian Candu react­ors that use nat­ural uranium from mines in Saskat­chewan, the BWRX­300 react­ors chosen for the SMRs rely on enriched uranium, which must be impor­ted from the United States, requir­ing much more robust secur­ity to avoid action­ movie scen­arios where radio­act­ive mater­i­als are hijacked by ter­ror­ists.

And, of course, the debate over nuc­lear power can’t avoid the ele­phant in the room.

The most recent nuc­lear melt­down, which occurred in Fukushima, Japan in 2011, promp­ted the long­ term evac­u­ation of a zone that extends up to 30 km from the acci­dent site and remains con­tam­in­ated with high levels of radi­ation. That acci­dent happened fol­low­ing the fourth most power­ful earth­quake ever recor­ded. The world’s only other nuc­lear cata­strophe to max out the rat­ing scale — the 1986 Chernobyl dis­aster, which left behind a vastly lar­ger exclu­sion zone — was caused by the con­flu­ence of flawed Soviet reactor design and oper­ator error.

No one, not even the fiercest crit­ics, says Ontario’s nuc­lear plants are vul­ner­able to the spe­cific events that caused these acci­dents. But it’s undeni­able that nuc­lear comes with nonzero risk.

If the Pick­er­ing nuc­lear plant were to exper­i­ence an acci­dent on the scale of Fukushima, a 30­km evac­u­ation zone would extend all the way to Yonge Street, for­cing mil­lions of people to aban­don their homes and busi­nesses with untold human and eco­nomic cost.

While a major nuc­lear acci­dent or a Hol­ly­wood hijack scen­ario are both extremely unlikely to hap­pen in Ontario, that doesn’t mean the pub­lic is going to for­get the risk.

Former Prime Min­is­ter Jean Chrétien and former Premier Mike Har­ris recently co­authored an oped arguing that in order to reap the full eco­nomic bene­fits of a new gen­er­a­tion of nuc­lear react­ors, the Cana­dian ­designed Can­dus must be used.

“In an increas­ingly uncer­tain world, energy secur­ity is national secur­ity,” they wrote. “If Canada does not choose Candu and instead goes with an Amer­ican tech­no­logy, that will mean the trans­fer of tens of thou­sands (and poten­tially hun­dreds of thou­sands) of jobs to the U.S. and abroad. The pain­ful changes we are cur­rently exper­i­en­cing in our auto­mobile industry in Ontario are a reminder of what hap­pens when we tie our for­tunes to for­eign tech­no­lo­gies and for­eign com­pan­ies.”

Asked about the choice of design for the SMRs, Lecce said Ontario is get­ting “first­ mover advant­age,” by tak­ing on the risk of build­ing the first reactor of its kind. The province will develop SMR expert­ise that will be highly sought after by other coun­tries look­ing to build small­ scale nuc­lear and has estab­lished 80 per cent of the sup­ply chain loc­ally.

“The Cana­dian sup­ply chain is at the heart of the gain of this project. We’re selling SMRs abroad. Ontario owns part of the intel­lec­tual prop­erty of the reactor design. Every time we sell, we make money,” he said.

Even though the first SMR hasn’t yet been built, Lecce has already announced deals to provide nuc­lear expert­ise to New York, Nova Sco­tia, New Brun­swick, Bel­gium and Bul­garia.

“Ontario is solid­i­fy­ing Canada’s global lead­er­ship in clean, emis­sions­ free nuc­lear power, and the world is watch­ing,” Lecce said at the announce­ment in Sofia, last month.

Mean­while, the first SMR is already behind sched­ule. In 2023, the province announced that it would be built by 2028. After a pro­trac­ted licens­ing pro­cess car­ried out by the Cana­dian Nuc­lear Safety Com­mis­sion, OPG now says con­struc­tion will be com­plete “by the end of the dec­ade” and “con­nect to the grid by the end of 2030.”

The aggress­ive timeline for these small nukes is part of the prom­ise that they will buck the tech­no­logy’s repu­ta­tion for being expens­ive and slow to build.

“We’re not talk­ing 20 years out. We’re talk­ing a mat­ter of another four ­odd years,” Lecce said.

By then, it will be a little clearer whether Ontario’s nuc­lear ambi­tion rep­res­ents foresight or folly.

Ontario needs to start build­ing big nuc­lear again – and fast!

This article was written by Andrew Clunis, Pres­id­ent Power Work­ers’ Union, and was published in the Toronto Star on December 12, 2025.

Ontario’s Inde­pend­ent Elec­tri­city Sys­tem Oper­ator (IESO) and oth­ers have iden­ti­fied a loom­ing elec­tri­city capa­city gap start­ing in 2035, with demand for elec­tri­city rising much faster than the province is build­ing new, clean gen­er­at­ing facil­it­ies. Accord­ing to the province’s Integ­rated Energy Plan, between now and 2050, Ontario could need 17,500 mega­watts (MW) of addi­tional nuc­lear gen­er­a­tion alone – the equi­val­ent of adding five new Dar­ling­ton-scale nuc­lear sta­tions.

Ana­lyses by the Power Work­ers’ Union sug­gests the gap could be much big­ger. While the IESO projects a 75 per cent rise in demand for elec­tri­city in Ontario, some experts indic­ate the actual need could be more than double today’s levels. Ful­filling such a power require­ment would be a sig­ni­fic­ant task, to say the least.

Ontario’s large react­ors have been the quiet work­horses of our clean-energy sys­tem for more than half a cen­tury. They have afforded the province one of the low­est-car­bon elec­tri­city grids in the world. The CANDU tech­no­logy that powers these react­ors today is Cana­dian-designed, Cana­dian-built and glob­ally respec­ted for its safety, reli­ab­il­ity and long oper­at­ing life. Nuc­lear also has one of the highest capa­city factors of any elec­tri­city source — over 90 per cent — and the smal­lest land foot­print per unit of energy pro­duced. That sta­bil­ity anchors Ontario’s low-car­bon grid.

To address the immin­ent elec­tri­city crunch, Ontario must start build­ing large-scale nuc­lear again. Ideally, the sooner, the bet­ter. The devel­op­ment pro­cess from plan­ning to engin­eer­ing and reg­u­lat­ory review to per­mit­ting and con­struc­tion time takes years. Delays have real costs.

Ontario is already build­ing more gas gen­er­a­tion to meet rap­idly grow­ing demand driven by elec­tri­fic­a­tion of trans­port­a­tion, heat­ing sys­tems, AI data centres and indus­trial pro­cesses. By invest­ing in nuc­lear now, pub­lic funds that would oth­er­wise be spent on addi­tional gas-powered car­bon-emit­ting gen­er­a­tion could be saved, and the trans­ition to Ontario’s net-zero elec­tri­city sys­tem exped­ited.

Small mod­u­lar react­ors (SMRs) could be part of the solu­tion. These innov­at­ive and prom­ising new tech­no­lo­gies are well suited to com­ple­ment large-scale nuc­lear work­horses needed to power high-demand growth regions like the Greater Toronto Area.

More import­antly, SMRs (typ­ic­ally up to 300 Mega­watts (MW)) will be par­tic­u­larly valu­able in loc­a­tions that require hun­dreds of MW of new car­bon-free elec­tri­city gen­er­a­tion rather than the thou­sands needed in Ontario’s major load centres. SMR’s “fit-for-pur­pose” scalab­il­ity, and pro­spect of shorter design and con­struc­tion timelines, have attrac­ted interest from mul­tiple provinces, indus­tries and the fed­eral gov­ern­ment.

Con­struc­tion of the G7’s first four SMRs is already under­way at the Dar­ling­ton site in Clar­ing­ton, Ontario.

Now there are even more reas­ons to get mov­ing quickly, includ­ing eco­nomic devel­op­ment, high-skilled jobs, indus­trial renewal and energy sov­er­eignty.

Canada’s trade rela­tion­ships are under­go­ing an unpre­ced­en­ted restruc­tur­ing that will take years if not dec­ades to develop and sta­bil­ize. In this envir­on­ment, Canada’s nuc­lear industry is not just a power­house, it’s an eco­nomic accel­er­ator.

Accord­ing to an eco­nomic impact study com­mis­sioned by the Cana­dian Nuc­lear Asso­ci­ation in 2024, the nuc­lear sec­tor con­trib­utes 22 bil­lion per year to GDP, and sus­tains approx­im­ately 80,000 highskilled jobs in engin­eer­ing, con­struc­tion, man­u­fac­tur­ing, min­ing and plant oper­a­tions. This industry study is con­sist­ent with fed­eral gov­ern­ment find­ings. Nat­ural Resources Canada stated in 2024 that over 75,000 Cana­dians are employed across the nuc­lear sup­ply chain and that the nuc­lear industry is a sig­ni­fic­ant con­trib­utor to GDP, gov­ern­ment rev­enue, and employ­ment. Canada’s nuc­lear sup­ply chain is dom­in­ated by domestic com­pan­ies, includ­ing over 250 firms con­cen­trated in Ontario’s indus­trial heart­land (rep­res­en­ted by the Organ­iz­a­tion of Cana­dian Nuc­lear Indus­tries). Employ­ing our uranium, tech­no­lo­gies and work­force keeps energy dol­lars and project man­age­ment in Cana­dian hands and under­pins our eco­nomy and sov­er­eignty.

More than half of Ontario’s elec­tri­city is pro­duced on three rel­at­ively small sites in Pick­er­ing, Tiver­ton and Clar­ing­ton. In the face of unpre­ced­en­ted elec­tri­city demand growth, neither Canada nor Ontario can afford to delay the launch of next gen­er­a­tion large-scale nuc­lear projects. This work should start at “Bruce C,” a pro­posed project to build up to 4,800 WW of nuc­lear power gen­er­a­tion on the exist­ing Bruce Power prop­erty in Tiver­ton. Wes­leyville is an exist­ing Ontario Power Gen­er­a­tion site near Port Hope that could sup­port up to 10,000 MW of new nuc­lear capa­city. These truly gen­er­a­tional projects will drive Cana­dian prosper­ity, cut emis­sions and pro­tect our energy sov­er­eignty.

Canada’s nuc­lear industry is essen­tial to meet Ontario’s massive demand growth for clean elec­tri­city and power the eco­nomy at a time when we need it most, espe­cially in light of the US gov­ern­ment’s tar­iffs affect­ing Ontario man­u­fac­tur­ing and heavy indus­tries. Doing so will also deliver on our net­zero-by-2050 com­mit­ment – all while build­ing on Canada’s long­stand­ing strengths as an energy super­power.

Power Work­ers’ Union calls on Ott­awa to treat new large-scale nuc­lear as a nation-build­ing pri­or­ity by fast-track­ing approvals through Major Projects des­ig­na­tion and provid­ing fed­eral fund­ing and Clean Eco­nomy Invest­ment Tax Cred­its to sup­port con­struc­tion. Large-scale nuc­lear, cap­able of deliv­er­ing large volumes of clean, reli­able and ‘round-the-clock power, will help secure Canada’s eco­nomic future and long-term energy sov­er­eignty.

Why Ford is bet­ting on nuc­lear power

This opinion was written by Martin Regg Cohn and was published in the Toronto Star on November 29, 2025.

Stephen Lecce wasn’t yet born when Pick­er­ing’s nuc­lear react­ors first came to life in the 1970s.

But he’s lived long enough to see the first batch of prob­lem­plagued nukes decom­mis­sioned over the last two dec­ades. Deemed unworthy for ret­ro­fit­ting, the four react­ors of Pick­er­ing “A” lie dormant and entombed beside Lake Ontario.

Now, Ontario’s 39­year­old min­is­ter of energy wants to rebuild and rein­carn­ate what remains of the Pick­er­ing fleet, part B — an aging cluster of four nukes from the 1980s whose polit­ical half­life has long been ques­tioned.

Sched­uled for moth­balling seven years ago, they are instead get­ting a new lease on life from Lecce. Thanks to a fresh invest­ment of $26.8 bil­lion, the four nukes are pro­jec­ted to last another 38 years once they are com­pleted over the next dec­ade.

The prob­lem with nuc­lear power, for those in polit­ical power, is that there are always so many vex­ing ques­tions:

How much will it really cost? Who will truly pay the bill? When will it ulti­mately come due? How safe is this redo?

The para­dox of nukes in this province is that the ques­tion of safety is rarely a debat­ing point. While nuc­lear power is polit­ic­ally radio­act­ive in Europe — prompt­ing a pan­icked Ger­many to shut down its react­ors — the major parties in this province are not so eas­ily spooked.

In fact, most politi­cians are sup­port­ive in prin­ciple of nukes, given their long­stand­ing safety record in Ontario. What they’re not all sold on is the rap­idly rising costs of nuc­lear power.

That’s because the third rail of elec­tri­city in Ontario is not so much safety or radio­activ­ity but afford­ab­il­ity and prox­im­ity. Ontario has long been ground zero for NIMBY oppos­i­tion to wind tur­bines and province­wide hys­teria over hydro prices.

That’s why a pre­vi­ous Lib­eral gov­ern­ment rejec­ted a refur­bish­ment of Pick­er­ing back in 2009 and took a rain check on buy­ing new nukes. That’s also why Doug Ford won polit­ical power in 2018, vow­ing to rip

Ontario politi­cians have always dreamed of cheap power, not just to pacify voters but also to attract for­eign invest­ment

up con­tracts for sub­sid­ized wind power while prom­ising to keep the price of elec­tri­city low.

All these years later, the premier presides over a gov­ern­ment that spends massive amounts of tax­payer dol­lars sub­sid­iz­ing power from all sources — not just wind but gas tur­bines and nuc­lear.

Dur­ing their years in oppos­i­tion, the Tor­ies joined the New Demo­crats in per­suad­ing Ontari­ans that elec­tri­city rates were unaf­ford­able. Facing a re­elec­tion debacle, the Lib­eral gov­ern­ment came up with an unsus­tain­able plan to sub­sid­ize hydro by hid­ing the true cost.

Today, Ford’s Tor­ies are per­petu­at­ing that ruse to the tune of $6.5 bil­lion in this fiscal year for “Elec­tri­city Cost Relief Pro­grams” bur­ied in the budget.

Against that back­drop, the massive costs of nuc­lear refur­bish­ment are destined to weigh down elec­tri­city bills long into the future. Lecce wouldn’t spe­cify the costs to con­sumers, just the bene­fits — 30,000 new con­struc­tion jobs and 6,700 per­man­ent pos­i­tions.

So why did Ontario reverse course after rul­ing out a Pick­er­ing refurb long ago? A major dif­fer­ence is that pro­jec­ted elec­tri­city demand had flat­lined in 2009 due to decreased man­u­fac­tur­ing demand even with an increas­ing pop­u­la­tion.

Today, by all accounts, elec­tri­city usage is destined to rise thanks to EV and AI — elec­tric vehicles and arti­fi­cial intel­li­gence, both of which are put­ting pres­sure on power gen­er­at­ors around the world. Ontario politi­cians have always dreamed of cheap power, not just to pacify voters but also to attract for­eign invest­ment — his­tor­ic­ally in man­u­fac­tur­ing, now in the indus­tries of the future.

What are the real­istic altern­at­ives, given Ontario’s tra­di­tional reli­ance on low­emis­sion nukes that helped the province rid itself of coal? Hydro­elec­tric power is largely tapped out at 24 per cent of Ontario’s energy mix, leav­ing nat­ural gas and oil (16 per cent), wind (nine per cent) and solar (one per cent).

Ques­tions will per­sist until the final bills come due — long after Ford and other polit­ical eld­ers have taken their leave of Queen’s Park. As for Lecce, will he still be around a dec­ade from now, presid­ing over rib­bon cut­ting cere­mon­ies at Pick­er­ing, won­der­ing if this big bet made sense?

Good ques­tion.

Ontario approves pickering nuclear plant refurbishment

This article was written by Matthew McClearn and was published in the Globe & Mail on November 27, 2025.

Work on the Pickering Nuclear Generating Station in Pickering, Ont., seen in 2020, is scheduled to begin in early 2027, with all units returned to service by the mid-2030s.

Crown corporation plans to replace steam turbines, steam generators and station’s water intake

The Ontario government has granted final approval for the refurbishment of four nuclear power reactors at Ontario Power Generation’s Pickering Nuclear Generating Station.

The approved budget for the project is $26.8-billion, more than double the cost of refurbishing the Darlington Nuclear Generating Station, which generates significantly more power. OPG says the Darlington project is on track to wrap up next year, meeting its original schedule and $12.8-billion budget.

The Pickering refurbishment is substantially more expensive in part because of the plant’s age. OPG plans to replace steam turbines, steam generators and the station’s water intake – expensive work that was deemed unnecessary at the newer Darlington station. There’s also been considerable cost inflation between the two projects.

Refurbishments are complex, expensive undertakings, presenting numerous technical and logistical challenges. When they don’t go as planned – as happened with New Brunswick Power’s Point Lepreau Nuclear Generating Station and at Pickering in the 2000s – it can cost taxpayers dearly.

Candu reactors can operate for about three decades between major overhauls. Their fuel and heavy water moderator must be removed, and much of the reactor must be disassembled. Crucial components, such as the pressure tubes, must be replaced. All the resulting radioactive waste must be stored. Meanwhile, utilities may elect to overhaul or replace other major components in the station, such as steam generators and turbines.

The idea of refurbishing the four reactors at Pickering B was previously considered beginning in 2006, but rejected a few years later. OPG’s board of directors warned that the units were at significant risk of performing poorly once returned to service, with high operating costs. The estimated refurbishment cost back then was $10.7-billion.

Work is scheduled to begin in early 2027, with all units returned to service by the mid-2030s.

Pickering B’s refurbished reactors, located around 35 kilometres from downtown Toronto, are expected to have a combined capacity of 2,200 megawatts, a boost of 100 megawatts. (Darlington’s capacity is about 3,500 megawatts.) Arne Wohlschlegel, managing director at Siemens Energy Canada, said part of the increase will come from design improvements to the steam turbines and turbine control systems. (Siemens Energy has been awarded the work to replace the turbines.)

Energy Minister Stephen Lecce said Wednesday at a news conference the station’s life will be extended by 38 years and that the project will create 30,000 jobs during construction and another 3,700 permanent positions.

Finance Minister Peter Bethlenfalvy cast the announcement as the latest example of his government’s firm commitment to the nuclear industry.

“I can guarantee you that we’ll have the nuclear industry’s back all the way through for the next 50 years,” he said.

Critics decried the decision. Mike Marcolongo, an associate director with Environmental Defence, described it as “a costly and high-risk choice that will push electricity bills higher.”

Pickering is Canada’s oldest commercial nuclear power station, featuring eight Candu reactors. Only the four newer B units, built in the 1970s and 80s, will be refurbished. They produce about one-tenth of Ontario’s power, and are expected to shut down in the third quarter of next year. There are no plans to overhaul the A units, which are permanently shut down.

Ontario has now marked nearly its entire commercial reactor fleet for refurbishment, and several units have already returned to service. Bruce Power is in the midst of refurbishing the eightreactor Bruce Nuclear Generating Station in Tiverton, Ont. The overhaul of the final Darlington unit is nearly complete.

The Pickering project requires approval from the Canadian Nuclear Safety Commission, which has a long record of greenlighting such applications from nuclear utilities. Pickering B was originally expected to close roughly a decade ago, but the CNSC has consistently granted permissions to extend its life.

Canada needs to step up. We need Candu nuclear technology

This opinion was written by Jean Chretien and Mike Harris, and was published in the Globe & Mail on November 19, 2025. Jean Chrétien is a former prime minister of Canada. Mike Harris is a former premier of Ontario. Both serve as co-chairs of Canadians for CANDU, a campaign by AtkinsRéalis to promote CANDU nuclear-reactor technology.

When we were both in office in the 1990s, Canada and China agreed to the sale of two Candu nuclear reactors, marking the largest commercial agreement between our two countries at the time.

Many decades later, we continue to see the benefits of that partnership and the construction of more than 30 other reactors built domestically and across the world: a strong supply chain, thousands of Canadian jobs and a global reputation for Canadian nuclear excellence. We advanced our interests as global energy suppliers then, and we can build on that momentum today.

In an increasingly uncertain world, energy security is national security. Every country that wants to chart its own future must be able to power its economy with confidence, independence and reliability. For Canada, that means using the technology we invented, perfected and continue to lead the world with: the Candu nuclear reactor.

A recent nuclear announcement from the government of the United States that offered support to their domestic technology makes one thing abundantly clear: We live in a world where large-scale nuclear deployments only succeed when they are backed by their host governments. Financial, regulatory, political and diplomatic support are needed for competitiveness.

For more than six decades, Candu technology, which is owned by Canadians, built by Canadians and driven by Canadian innovation, has powered our homes, businesses and hospitals with clean electricity. It has produced life-saving medical isotopes and helped establish Canada as one of the world’s most trusted nuclear innovators. All this, plus it is fuelled by natural uranium, abundant in Canada.

No foreign-designed reactor can be built or adapted to Canadian safety standards without reliance on enriched fuel that must be processed abroad and imported into Canada.

For more than six decades, CANDU technology, which is owned by Canadians, built by Canadians and driven by Canadian innovation, has powered our homes, businesses and hospitals with clean electricity.

In today’s protectionist world, that dependence poses a real risk. Candu avoids it entirely. Our reactors use natural uranium, mined and refined right here at home, in Saskatchewan and Ontario. This creates a homegrown fuel supply that can’t be disrupted by tariffs, trade wars or reactionary measures by unpredictable political actors around the globe.

The American strategic alignment changes the global nuclear landscape. Washington is now putting its considerable financial heft behind its own domestic nuclear technology. The implications for Canada are profound. If the U.S. is rallying behind its homegrown nuclear industry, then Canada must do the same. We must ensure that Canada remains competitive, not only for the sake of our energy security, but also for the thousands of Canadian workers and suppliers whose livelihoods depend on this sector.

We want to be clear: If Canada does not choose Candu and instead goes with an American technology, that will mean the transfer of tens of thousands (and potentially hundreds of thousands) of jobs to the U.S. and abroad. The painful changes we are currently experiencing in our automobile industry in Ontario are a reminder of what happens when we tie our fortunes to foreign technologies and foreign companies.

If Canada wants to truly be considered an energy superpower, we must first demonstrate confidence in our own technology. We cannot market and sell Canadian tech abroad if we do not invest in it at home. By choosing Candu for our next wave of large-scale nuclear builds, we send an unmistakable message to international partners: Canada stands behind its own technology.

Candu’s proven tech has been successfully deployed in Ontario and around the world for generations, with technology enhancements ready to deliver even greater efficiency to meet Ontario’s growing electricity demand. More than 90 per cent of Candu’s supply chain is domestic, concentrated in Ontario, a province facing significant trade challenges with the U.S. Investing in Candu directly supports Canadian steel, construction, manufacturing and skilled trades.

This is a blueprint for national independence. As the federal government seeks to support skilled trades workers, Candu offers a ready-made solution. The sooner approvals are made, the sooner more high-value, highskill jobs are available. Candu means real, lasting opportunity for Canadian workers and Canadian industry.

The choice of Candu technology for new builds in Ontario is about more than power generation: It’s about leadership. When we choose our own technology, we demonstrate to the world that Canada is serious about its energy ambitions and capacity to compete globally.

Ontario boosts rebates to cover hydro prices

Rate increase caused by higher nuc­lear costs, spend­ing on elec­tri­city­con­ser­va­tion pro­grams

This article was written by Marco Chown Oved and was published in the Toronto Star on November 7, 2025.

The price of elec­tri­city in Ontario just jumped by nearly 30 per cent, though few people may have noticed.

That’s because the price hike was almost entirely absorbed by a near­ doub­ling of the Ontario Elec­tri­city Rebate, which now cov­ers nearly a quarter of the cost of power to con­sumers.

While the net res­ult on res­id­en­tial hydro bills is min­imal, the increase in the elec­tri­city sub­sidy will cost tax­pay­ers an estim­ated addi­tional $2 bil­lion per year, on top of the $6.5 bil­lion the province already pays to reduce the cost of power.

As a res­ult, power sub­sidies now make up the major­ity of the pro­vin­cial defi­cit, which was pro­jec­ted to be $14.6 bil­lion this year.

“That’s money com­ing out of the pro­vin­cial budget, which oth­er­wise would have gone to defi­cit reduc­tion, schools and hos­pit­als, and instead is going to effect­ively social­ize the cost of these increases in elec­tri­city costs,” said Mark Win­field, a polit­ical sci­ence pro­fessor who stud­ies elec­tri­city policy at York Uni­versity.

“The polit­ical cost of mak­ing people pay for these increases would be unac­cept­able,” he said, not­ing that hydro prices were a major cam­paign issue for Ford’s elec­tion in 2018. “So, instead, they hide these costs.”

Win­field cal­cu­lated the costs of the exist­ing elec­tri­city sub­sidies and estim­ated the $2 ­bil­lion ­a ­year cost of the increase based on pro­vin­cial budget doc­u­ments and a Fin­an­cial Account­ab­il­ity Office report.

“After a dec­ade of hydro hikes under the Lib­er­als that cost work­ing fam­il­ies and seni­ors an extra $1,000 a year, our gov­ern­ment made a clear com­mit­ment: to keep energy rates stable and afford­able. Since 2018, we’ve delivered on just that — ensur­ing elec­tri­city rates have stayed near or below infla­tion,” wrote Chelsea McGee, a spokes­per­son for Energy Min­is­ter Stephen Lecce.

The hydro rate increase, which came into force on Nov. 1, was caused by higher­than­ expec­ted nuc­lear costs and an increase in spend­ing on elec­tri­city­ con­ser­va­tion pro­grams, accord­ing to the Ontario Energy Board.

Ontario is plan­ning a massive increase in power gen­er­a­tion as both industry and people elec­trify. From elec­tric steel mak­ing to EVs and heat pumps, the province anti­cip­ates that it will need 75 per cent more elec­tri­city by 2050.

To meet that demand, Premier Doug Ford has turned to nuc­lear, start­ing con­struc­tion on the first small nuc­lear react­ors (SMRs) in the west­ern world, pro­pos­ing two new full­sized react­ors and refur­bish­ing Ontario’s exist­ing fleet.

Because Ford has alloc­ated $21 bil­lion for four SMRs, and bil­lions more for new full­sized react­ors, Win­field says Ontari­ans can expect fur­ther hikes to hydro prices in the future.

This raises chal­lenges for both eco­nomic com­pet­it­ive­ness and com­bat­ing cli­mate change, said Win­field. “As elec­tri­city costs go up, the notion of elec­tri­fy­ing things like space heat­ing or trans­port­a­tion or indus­trial pro­cesses is going to get a whole lot less attract­ive,” he said.

When Ford cam­paigned to be premier, he prom­ised to lower elec­tri­city bills by 12 per cent, a prom­ise he later claimed to have kept, even though hydro rates went up.

Aver­age time­ of­ use elec­tri­city rates have risen 57 per cent since May 1, 2018, though much of that increase has been off­set by an increase to the elec­tri­city rebate that covered eight per cent of the pre HST cost of power on con­sumers’ bills that year, and now cov­ers 23.5 per cent, accord­ing to the OEB.

Just before the rate increase came into effect, Ontario’s Inde­pend­ent Elec­tri­city Sys­tem Oper­ator (IESO) released its report on the future of the elec­trical grid in Toronto, say­ing a new under­wa­ter trans­mis­sion line will be neces­sary to meet grow­ing power demand, which is expec­ted to double by 2043. The report also recom­men­ded keep­ing the Port Lands gas plant online past its cur­rent con­tract ter­min­a­tion in 2034.

Ontario has not con­struc­ted any new wind or solar in the seven years since Ford became premier.

The rebate increase will cost tax­pay­ers an estim­ated $2 bil­lion more per year, mak­ing power sub­sidies the major­ity of the pro­vin­cial defi­cit

Western provinces want nuclear power plants. Are they ready to buy this time?

This article was written by Matthew McClearn and Emma Graney, and was published in the Globe & Mail on October 29, 2025.

Since previous attempts to bring nuclear power to Western Canada’s electricity grids, the industry’s cost disadvantage has grown. Wind and solar generation, meanwhile, have declined dramatically in price.

Previous bids to bring power plants to Saskatchewan and Alberta failed, but both provinces are newly optimistic

In Jeremy Harrison’s telling, one of the most crucial decisions in the history of Saskatchewan’s energy sector has already been made: It will build nuclear power plants.

“The government has made the binary decision that we are going to be moving to nuclear baseload power generation,” Mr. Harrison, the province’s Minister of Crown Investments Corporation, declared in an interview.

Saskatchewan, which explored building nuclear plants more than 15 years ago, has only just started. Its Crown power utility, SaskPower, has established a subsidiary called SaskNuclear, and earlier this year the federal government announced a contribution of $80-million to support the utility’s early preparations. The province wants the federal government to pay for three-quarters of the cost of its first reactor.

Meanwhile, conversation around incorporating nuclear into neighbouring Alberta’s grid has just begun. A new Nuclear Energy Engagement and Advisory Panel has been set up to advise Alberta’s government about its potential role in advancing a nuclear energy industry, and Utilities Minister Nathan Neudorf is optimistic about how that might roll out.

Alberta’s power market differs markedly from others in Canada, in that it’s privatized. That means the government is “trying to be as agnostic as possible” on what technology might fit into the province’s grid, Mr. Neudorf said in an interview. A small handful of private developers are promoting early-stage projects.

“We want to let the private market do their work and facilitate their pursuit of this, so that we allow for that good competition and the best fit to rise to the top without government tipping the scales one way or the other,” he said.

Alberta previously considered building nuclear plants but later stood down. Concerns about risk to taxpayers prevailed both there and in Saskatchewan, as did antinuclear sentiment. But recent opinion polls suggest a change of heart: A 2023 Angus Reid poll found residents of both provinces to be more enthusiastic than respondents in Ontario and New Brunswick, which already have nuclear plants.

Ontario’s decades-long journey to building more than 20 nuclear reactors had rocky periods, but they became the backbone of its power grid. New Brunswick’s lone nuclear station, though, has placed its government in a financial bind, and can be regarded as a cautionary tale for less populous provinces.

If Alberta and Saskatchewan truly are committed to nuclear power, what can they do to avoid the pitfalls that have plagued other nuclear jurisdictions while maximizing the benefits?

A MOMENT OF OPTIMISM

Reactors’ ability to churn out copious quantities of electricity has contributed to perceptions that their moment has finally arrived in Western Canada.

“What power utilities across North America are seeing is almost unprecedented load growth demand, and projections out to 2050 showing potentially doubling of load growth,” Mr. Harrison said.

Mr. Neudorf says three notable changes in the power conversation explain the West’s growing interest in nuclear – concern about greenhouse-gas emissions, optimism that the cost of nuclear is shrinking and a wider realization that amid geopolitical and supply chain disruptions, “trusted partners may not be as trusted as they were before.”

While both governments remain strongly supportive of burning hydrocarbons for power – Saskatchewan recently unveiled plans to refurbish three coal-fired plants – they present nuclear as an attractive source of “baseload” power. This refers to the amount of energy required to meet an electrical grid’s minimum level of demand – say, during the middle of the night.

Baseload power indeed ranks among nuclear’s strengths.

SaskPower’s plans have gradually evolved over the past several years. It selected the BWRX-300 (an American-Japanese reactor planned for first construction in Ontario) a few years ago and identified potential sites, including in the Estevan and Elbow regions, where it might build two reactors.

EAC Capital Limited Partnership (which operates as Energy Alberta) proposes to build what would be among Canada’s largest nuclear plants near Peace River, Alta., at 4,800 megawatts. It startled some observers earlier this year by commencing an impact assessment with two federal regulators, the Impact Assessment Agency of Canada and the Canadian Nuclear Safety Commission. It plans to commission its first reactor a decade from now, with the other units entering service in 2038, 2040 and 2043.

But in August the company asked the CNSC to suspend the impact assessment, asserting a need for additional time to consult Indigenous communities.

Chief executive officer Scott Henuset says while the “entrepreneurial attitude of Albertans” is the driving force behind the project, there are wider opportunities for Western Canada if it embraces nuclear. Alignment between the provinces and the Northwest Territories would create a more stable grid in the West, he said, which would help fuel industries such as critical minerals, mining, liquefied natural gas facilities, the oil sands and population growth in general.

“The provinces shouldn’t be fighting amongst each other, and the proponents either,” he said. “We should all be banding together to make sure that we have enough power supply in Western Canada to facilitate our lights being on at our homes and our fridges being cold, as well as industry growth and economy growth, so that we can stay competitive.”

Edmonton-based independent power producer Capital Power (which owns a fleet of natural-gas plants across North America) announced a partnership with Ontario Power Generation nearly two years ago to explore developing small modular reactors, or SMRs, at 11 candidate sites within a 150-kilometre radius of Edmonton. Their joint reports, released earlier this year, contained only generic information, and Capital Power has barely discussed nuclear in its recent communications with investors; the company declined an interview request from The Globe and Mail to discuss its plans.

Founded in 2022, Calgarybased startup Nucleon Energy previously said it’s predeveloping two projects in Alberta (one in Bonnyville, another in the Peace River region) but has yet to apply for permits. Its CEO, Dustin Wilkes, said Nucleon is open to using a wide variety of reactors, but the company announced this year it’s exploring potential deployment of the ARC-100, a conceptual SMR from a small New Brunswick developer.

A HISTORY OF WINDOW-SHOPPING

Saskatchewan’s fascination with nuclear power is motivated in part by concerns about its uranium mining and milling sector, for which it is known internationally. The problem is that its nuclear value chain essentially stops there: It doesn’t process its own uranium for use in reactor fuel, let alone consume that fuel to generate power.

Anxieties mounted in the late 2000s when Saskatchewan lost its status as the world’s largest uranium producer. An industry-dominated group called the Uranium Development Partnership recommended the province build 3,000 megawatts of nuclear generation capacity.

Alberta, though, had its own plans. Industry accounts for roughly three-quarters of the province’s energy use. Many industrial processes need not only electricity but also steam; nuclear plants can produce both. Energy Alberta rose during this era: Established in 2005, it drew up initial plans for a Peace River plant before being purchased by Bruce Power, a dominant player in Ontario’s nuclear industry, in 2007.

Yet both governments’ ardour quickly cooled. Saskatchewan’s premier at the time, Brad Wall, acknowledged nuclear’s high costs and public opposition. In 2009, his government kiboshed Bruce Power’s proposal to build a large nuclear power plant in Saskatchewan. That same year, Ed Stelmach, then Alberta’s premier, described nuclear power as a “viable option” but vowed no public money would be spent on it.

Jason Wang, an analyst with the Pembina Institute, an energy think tank, said the lack of nuclear proposals since then is revealing.

“Any time between then and now, private entities could have said, ‘We’d like to build a project and work with the government on developing all the regulations necessary to execute that,’ ” he said.

“But we haven’t seen it.”

THE COST CONUNDRUM

The nuclear industry’s cost disadvantage has grown since then. The only reactor constructions in North America during that period went dramatically over budget and blew past deadlines. Wind and solar generation, meanwhile, declined dramatically in price.

SMRs were intended to bridge that gap, but the promised savings haven’t materialized. Ontario Power Generation expects to pay $20.9-billion for a 1,200megawatt station consisting of four BWRX-300s, far above optimistic estimates by SMR vendors.

The price for a 1,000-megawatt Monark, the reactor proposed for construction in Peace River, has not been disclosed. But its developer, AtkinsRéalis Group Inc., has estimated a single unit might cost between $10-billion and $15-billion.

Nuclear cost estimates are famously unreliable. Mr. Wang said the Pembina Institute analyzed recent nuclear projects globally over a six-year period, and found that the average cost overrun was 125 per cent.

All considered, it’s worth asking whether Alberta and Saskatchewan can really afford nuclear plants. The Alberta government’s total operating expenses were $62-billion for the 2024-25 fiscal year – that’s for health, education, child care, social services, the legislative assembly and everything else. As for Saskatchewan, its total revenues amounted to about $21-billion, and expenditures were slightly greater.

Mr. Harrison said Saskatchewan will only build reactors that have already been constructed elsewhere, which he expects will drive down costs and minimize risks. He expects federal financing, and pointed to Britain’s Sizewell C, priced at £38-billion or roughly $70-billion, as one nuclear project that has attracted private financing.

Proponents argue that nuclear’s large upfront costs must be weighed against alternatives over plant lifetimes. Alberta Premier Danielle Smith appears to accept that logic, asserting in late August that nuclear is “low-cost in the long run.”

WATER, WASTE AND WAITING

In another stark contrast with alternatives, nuclear plants can easily take a decade or two to plan and construct – a drawback for jurisdictions with immediate wants and needs.

Ms. Smith is eager to attract data centres to Alberta, and casts reactors as a natural fit. Yet, Mycle Schneider Consulting’s latest report on the nuclear industry, published in September, pointed to such projects’ penchant for lengthy construction schedules and frequent delays.

“Building new nuclear plants for data centers appears incoherent,” the report concluded.

“Time horizons do not match: while data centers need power in the short term, nuclear power plants need many years to develop, plan, and build; competing solar power plants can be set up within months.”

Alberta and Saskatchewan present additional challenges for building nuclear plants. The simplest and cheapest way to cool a nuclear station is by drawing water directly from an ocean, large lake or river. Partly for this reason, Ontario’s were built on the shores of the Great Lakes, Quebec’s on the St. Lawrence River, and New Brunswick’s alongside the Bay of Fundy.

Water is generally scarcer across swaths of Western Canada, particularly southern Alberta. Alternative cooling methods exist, including cooling towers and evaporation ponds and nuclear plants have been built in arid regions. But alternatives can add to cost and also consume large quantities of electricity, further eroding a plant’s economic attractiveness.

Radioactive spent fuel requires permanent disposal, and this is again tricky and expensive. Canada’s nuclear industry proposes building an underground facility known as a deep geological repository in Northern Ontario, at an estimated cost of $26-billion. It’s unclear whether plants in Western Canada would ship their spent fuel there, or the provinces would need to build their own.

For Mr. Harrison, failure is not an option; Saskatchewan has no fallback plan for achieving its long-term electricity and decarbonization targets.

“We’re committed to having nuclear being the evolution to where we go,” he said. “We’re going to work through this.”

Brookfield, Cameco join U.S. in $80-billion nuclear program

This article was written by Matthew McClearn and James Bradshaw, and was published in the Globe & Mail on October 29, 2025.

The Alvin W. Vogtle Electric Generating Plant in Waynesboro, Ga., is shown in May. The U.S. government has signed an agreement with Westinghouse Electric Co. and its Canadian owners – Brookfield Asset Management and Cameco Corp. – intended to spur construction of as many as eight large nuclear reactors.

Owners of Westinghouse will work with Japanese vendors to build reactors in the United States

U.S. reactor vendor Westinghouse Electric Co. and its Canadian owners, Brookfield Asset Management and Cameco Corp., have signed an agreement with the United States government intended to spur construction of as many as eight large nuclear reactors.

Described as a “binding term sheet,” the agreement requires the U.S. government to arrange financing and facilitate permitting approvals for reactors costing at least US$80-billion, the parties announced on Tuesday. The proposed reactors would be built on U.S. soil and are intended to power data centres and artificial intelligence computing capacity.

A statement issued by the White House on Tuesday said that as part of a bilateral agreement, the Japanese government and various Japanese companies had committed to provide up to US$332-billion to support “critical energy infrastructure,” including construction of nuclear reactors from Westinghouse and GE Vernova Hitachi Nuclear Energy, an American-Japanese vendor.

The announcement came after U.S. President Donald Trump met with newly elected Japanese Prime Minister Sanae Takaichi in Tokyo on Tuesday. Japan’s motives for funding the U.S. projects were unclear.

Separately, the Japanese government said it would spend up to US$100-billion on reactors, adding that Japanese suppliers such as Mitsubishi Heavy Industries and Toshiba Group could be involved.

The Westinghouse deal suggests a new role for the U.S. government in power plant construction. Whereas utilities and state governments traditionally had the final say in greenlighting multibillion-dollar nuclear plants, under its agreement with Westinghouse the federal government is responsible for making the final investment decision.

Koroush Shirvan, a professor at the Massachusetts Institute of Technology’s nuclear engineering department, said it’s a strong indication the U.S. government wants to catch up with China and Russia, which have dominated reactor construction for decades.

“The reason China and Russia are winning the nuclear constructing battle is that the government has a stake in it – it’s all government-driven,” he said.

The deal also exemplifies the U.S. administration’s increasing willingness to intervene directly in key sectors. Under Mr. Trump, the U.S. has taken stakes in major companies such as Intel and US Steel, as well as Canadian critical-minerals companies Lithium Americas Corp. and Trilogy Metals Inc.

Providing certain milestones are met – including Westinghouse reaching a valuation of US$30-billion – the company would be compelled to hold an initial public offering, and the U.S. government will be entitled to buy a minority equity stake in the company, up to about 8 per cent of the outstanding shares.

That stake could be worth more than US$2.5-billion, and would be granted to recognize the government’s role in deploying “its financial, regulatory, policy and diplomatic tools to support the objectives of the partnership,” Cameco said in a news release.

Chris Gadomski, head of nuclear research for BloombergNEF, said U.S. state ownership of major nuclear companies would be “a two-edged sword.” The government can bring the billions in financing that are crucial for nuclear projects, he said, but U.S. and French nuclear companies with significant state ownership often haven’t performed well.

Mr. Gadomski added that key details were absent from the Westinghouse announcement, including the locations of the proposed plants.

“I would feel a lot more confident about the substance of this press release if they had a hyperscaler or a utility saying, ‘Yeah, we’re really excited – we’re going to have an AP1000 on our site.’”

Westinghouse’s main offering is its AP1000 reactor, a large pressurized water reactor with a capacity greater than one gigawatt. (A gigawatt would provide enough electricity to power about one million homes.) Two are operating in the U.S. and four in China, and more than a dozen others are under construction. Many of Westinghouse’s competitors promote reactors that haven’t yet been completely designed, let alone licensed or constructed.

But the reactor’s history also highlights the challenges of building nuclear plants in North America.

Two AP1000s were constructed at the Vogtle Electric Generating Plant in Georgia and began operating in 2023 and 2024, respectively, but both suffered years-long delays and large cost overruns. (The two units ultimately cost US$34-billion combined.) Construction of two partly-completed AP1000s, at the V.C. Summer Nuclear Generating Station in South Carolina, was terminated in 2017.

The U.S. has 94 operational reactors, but the fleet is among the world’s oldest, and no reactors are currently under construction. In May, Mr. Trump signed an executive order demanding that the Department of Energy work with the nuclear industry to begin construction of 10 new large reactors by 2030.

Prof. Shirvan noted that when construction, financing and grid connection costs are all considered, it can cost US$15-billion or more to build new reactors. But with several AP1000s already constructed, the risk of cost and schedule overruns is greatly reduced.

“The biggest risk is you build and nobody comes to buy the power,” he added.

“Because at the end of the day, a gigawatt is a gigawatt, and with 10 of them we’re at 10 gigawatts. That’s a lot of power.”

Brookfield’s private equity arm first acquired Westinghouse out of bankruptcy for US$4.6-billion in 2018, from Toshiba Corp, using a mixture of cash and debt. Under a subsequent turnaround plan, Brookfield narrowed Westinghouse’s focus to nuclear, cut costs and bulked up the company through acquisitions.

In 2022, Brookfield sold Westinghouse for US$4.5-billion plus more than US$3-billion in assumed debt to its own renewable energy arm, which took a 51-percent stake in the business, and to Cameco which bought the remaining 49-per-cent interest.

The deal, which closed in 2023, gave Brookfield’s private equity business a sixfold return on its investment, while keeping the asset manager’s majority control of Westinghouse. At the time, nuclear power was enjoying renewed popularity after Russia’s invasion of Ukraine sent energy prices in Europe soaring.

Brookfield has been an investor in power and renewable energy for decades, starting with the purchase of hydroelectric assets in the 1980s. Nuclear energy has emerged as a key part of its strategy over the past few years, as the company bet on a revival driven by tailwinds in the decarbonization and electrification of energy sources, and the heightened focus on energy security amid wars and trade disputes.

Last week Santee Cooper, South Carolina’s state-owned power producer, announced its board of directors had entered into exclusive negotiations with Brookfield to complete the two AP1000s at V.C. Summer. Under an arrangement described as a “letter of intent,” the two companies agreed to commence a sixweek process to select a project manager and consider construction providers to resume the work, while also entering into discussions with potential buyers of the power the reactors would generate.

Ott­awa, province dir­ect $3B for react­ors

This article was written by Ryan Tumilty and was published in the Toronto Star on October 24, 2025.

As Prime Min­is­ter Mark Car­ney announced a $2­ bil­lion invest­ment in new Ontario nuc­lear react­ors, which have been flagged as poten­tial projects in the “national interest,” sources inside Premier Doug Ford’s gov­ern­ment said that des­ig­na­tion is no longer something they want.

Car­ney and Ford appeared together at the Dar­ling­ton power plant in Bowman­ville, Ont., on Thursday morn­ing to announce a com­bined $3­bil­lion invest­ment in small mod­u­lar react­ors (SMRs).

The SMRs have been marked as poten­tially in the “national interest” projects by the fed­eral gov­ern­ment and were among the first projects Car­ney referred to the gov­ern­ment’s Major Projects Office in Septem­ber. Under the Car­ney gov­ern­ment’s One Cana­dian Eco­nomy Act, if the Major Projects Office des­ig­nates a project as “in the national interest,” it is exped­ited through the reg­u­lat­ory pro­cess and must be reviewed within two years.

In a let­ter sent this sum­mer, Ford high­lighted Ontario’s broad plans for nuc­lear expan­sion, which include the Dar­ling­ton react­ors, as projects the gov­ern­ment should con­sider as in the national interest.

But a Ford gov­ern­ment source said that is something they don’t want for the province’s nuc­lear plants, nor for a pro­posed road to the Ring of Fire min­ing region.

“We don’t want to be des­ig­nated” a source said, speak­ing on back­ground because they were not author­ized to speak pub­licly.

A source said work­ing with the Car­ney gov­ern­ment’s Major Project’s Office has been a good exper­i­ence, but they don’t believe their projects need the hands­on atten­tion. Instead they hope the fed­eral gov­ern­ment simply improves the approval pro­cess for future nuc­lear projects. As an example, they sug­ges­ted any future Cana­dian power pro­vider that wants to use the same model SMR as Ontario should have a more exped­ited review, because the tech­no­logy has already been stud­ied.

A Ford gov­ern­ment source said they are no longer inter­ested in a “national interest des­ig­na­tion” for the Ring of Fire road project because they believe it can be exped­ited if the fed­eral gov­ern­ment simply “gets out of the way.” The province and the fed­eral gov­ern­ment have both launched reviews of the road projects, which would improve access to com­munit­ies north of Tim­mins and Thun­der Bay, allow­ing valu­able min­eral depos­its to be mined.

A fed­eral gov­ern­ment source, who also spoke on back­ground, said the gov­ern­ment didn’t open the Major Projects Office to cre­ate more of a reg­u­lat­ory bur­den and wants will­ing part­ners on any projects.

The source said with the Ring of Fire in par­tic­u­lar many Indi­gen­ous com­munit­ies believe they have a dir­ect rela­tion­ship with the crown through the fed­eral gov­ern­ment and will want Ott­awa to be involved.

Premier Doug Ford at the Dar­ling­ton com­plex Thursday.